Daibiru, Sankei Building Join Osaka Gas in Backing 15MW Renewable Data Centre in Hokkaido

By: IDCNOVARegion: East Asia
Japanese office landlords Daibiru and Sankei Building are taking minority stakes in a 15-megawatt renewable-powered data centre in Hokkaido developed by Tokyu Land and Flower Communications, joining Osaka Gas Urban Development as investors in the project, the companies announced. The three parties are investing in Ishikari Renewable Energy Data Center No.1, with Daibiru and Sankei Building expecting to complete their investments by March 31, 2027. Financial terms were not disclosed.

The investment marks a strategic diversification for both landlords. Daibiru, a wholly owned subsidiary of shipping group Mitsui OSK Lines, is making its first-ever data centre investment as it branches out from an office portfolio concentrated in Osaka and Tokyo. Sankei Building, which opened its first facility — the Optage Sonezaki Data Center in Osaka's Higashi-Umeda district — in 2025, is expanding its footprint in the sector. Daibiru said in a release that the investment is part of its long-term plan to expand investment in Japan and overseas, aiming to "capture new business opportunities in this growth sector and build up its expertise in the data centre business."

The 10,065 square metre (108,338 square foot) facility, located in the Ishikari Bay New Port area, has 15MW of incoming power capacity. Construction was completed on March 27 and the centre began service on August 1. Tokyu Land and Flower Communications managed development for the project company, with Agility Asset Advisers serving as asset manager. The facility draws all its electricity from renewable generation in Ishikari, a city on Hokkaido's western coast facing Ishikari Bay and the Sea of Japan. Tokyu Land and the city have used private power lines to deliver locally generated electricity directly under a power purchase agreement, while Hokkaido's mild climate can help reduce demand for mechanical cooling. GMO Internet plans to open a site for its GPU cloud service by year-end in part of a data hall operated by BroadBand Tower, supplying computing power for AI workloads including training and running large language models.

Tokyu Land and its partners cited difficulty securing additional power in the Tokyo area as a reason for choosing Ishikari, as well as the value of placing computing capacity far enough from the capital to help keep services running if a disaster disrupts the Tokyo region. About 90 percent of Japan's data centres are concentrated in Greater Tokyo and Greater Osaka, according to JLL, which expects new supply in both established clusters and emerging locations as rising AI use adds pressure on power supplies. Greater Tokyo's operating data centre capacity rose 18 percent year-on-year to 1,397 megawatts in the first half of 2026, even as vacancy fell to 4.4 percent, according to Cushman & Wakefield. Data centre research firm DC Byte said in June that constraints on land and power in Tokyo were drawing developers to Osaka and prompting interest in markets farther afield, including Kyushu.

The Hokkaido investment comes amid a surge in Japanese data centre deal activity. Greater Osaka was home to Asia Pacific's largest transaction of a single data centre in the first nine months of 2026, with MSCI recording $992.1 million for the Colt DCS Keihanna facility, while Keppel DC REIT and its sponsor agreed in September to acquire a 90 percent interest in two hyperscale facilities in Inzai from a venture of GIC and Equinix, in a deal valuing the properties and their operating company at JPY 190 billion ($1.2 billion). The expansion has come with setbacks, however, as shares in Tokyo-listed AI infrastructure provider Datasection dropped 43 percent over three sessions last week after the company cut its annual revenue forecast by 89 percent to JPY 17.3 billion, citing a major computing contract cancelled in August and delays in bringing data centres online.